Grandview Extraction Facility
Case Studies
This project has taken 7 months to construct around 22 containers into a fully functional interconnecting, Extraction, Processing, and Storage production facility.
The Extraction Facility
We have recently completed a facility in the North West. This project has taken 7 months to construct around 22 containers into a fully functional interconnecting, Extraction, Processing, and Storage production facility. The facility includes 6 freezers, which have been used to store products prior to entering the Extraction process. We have rooms for Extraction, Post Extraction, Bathrooms, Shower Facilities, Mechanical, Vault, and Storage all included.
“We are very proud of this project, it has run smoothly and at the end of the day we have a very happy client. We look forward to working with them on all future projects.”
– Mark Pike