Vapen MJ Ventures Extraction Lab
Custom-design, build, and installation of a 45 ft. extraction lab in Jamaica
We recently had the opportunity to partner with Vapen MJ Ventures on an extraction lab. We custom-designed, built, and installed a 45 ft. lab in Jamaica. There were a number of challenges with which we were faced, but we are dedicated to building the best solutions for your extraction needs.
Because we were building an extraction lab for Jamaica, we needed to address the electric frequency difference to ensure safety and effectiveness. The electric frequency in Jamaica is 50 Hertz but the equipment installed was CAPNA Fabrications Ethos 6 and Ares Falling firm along with POPE Stills all run on 60 Hertz. Thus, we needed to install a VFD (Variable Frequency Drive) to convert the power from 50 to 60 Hertz. We are proud to have partnered with Vapen MJ Ventures to design a cost-effective and scalable extraction lab solution while overcoming international electrical frequency differences to install an outstanding extraction solution for our client.